Water Project Updates
Standish Township has entered into an agreement with Bay County to become a wholesale water customer after encountering challenges with original water main route through Pinconning Township. The new route
Sewer Project Updates
Water Project - Engineer Update
The watermain has been connected at Lapan road and 97% of watermain is installed. All tests on the watermain from Lapan Road to the railroad tracks on McLarty Road have
The contractor has approximately 1,600’ remaining of watermain to installed South of Bay Arenac Line on North Shore Road. Once the watermain is installed they will continue with installing hydrants
Sewer Project - Engineer Update
A high level estimate and action plan for a wastewater treatment lagoon has been developed. A wetland delineation of the proposed site has been completed. The next step will be
Evaluation of potential sewer routes is ongoing. We continue to look for the most cost effective and efficient route for the sewer forcemain. – Fleis & VandenBrink