A high level estimate and action plan for a wastewater treatment lagoon has been developed. A wetland delineation of the proposed site has been completed. The next step will be to meet with EGLE to discuss the Lagoon option.
Whites Beach Rd/Lafave Rd Site Update – Consumers Energy is finalizing the design to bring in power and gas to the site and will be submitting a cost and installation date. Electrical quotes are being evaluated. Contractor to install the remaining watermain pipes into the building to prep for the concrete floor to be poured in the coming weeks. Once the concrete is installed the insulation and wall sheeting will be installed followed by the interior watermain piping, booster pumps, chemical feed system, and electrical.