The contractor has approximately 1,600’ remaining of watermain to installed South of Bay Arenac Line on North Shore Road. Once the watermain is installed they will continue with installing hydrants and valves. The last segment of watermain to be installed is the railroad crossing on McLarty Road. The watermain will be tested before making the connection to the existing watermain at Lapan Road. The booster pumps and chemical feed system have a tentative delivery date of early September and will be installed up on delivery. – Fleis & VandenBrink